Our Remodel ~ 2007
9289a.jpg
 
9303a.jpg
 
0497a.JPG
April 24 - Health Dept. (sewer) Inspection
resulted in a tree being cut down
0496b.JPG
 
0495a.JPG
 May 21 -Steel siding is removed
(looks better already!)
0501a.jpg
 
0500a.JPG
and the patio is also removed
0498a.JPG
 
 0504a.jpg
 
0506a.jpg
this is the stack of wood from the patio
and styrofoam from the house
(doesn't look like that much)
 0505a.jpg
May 22 - insulation was put in the walls 
0508_2.JPG
May 23 - holes were plugged
 0507_3.JPG
May 24 - all new windows were installed
0509_2.JPG
May 25 - new sliding door installed 
0511.JPG
and we wait
Felix_the_Cat_animated.gif
 
June 11 - removed original siding
0515.JPG
 
0514.JPG
 
0517.JPG
 
0517a.JPG
 
0516.JPG
June 15 - picked up permit for addition
These are the computerized drawings
of the new addition
design_1.jpg
 
design_2.jpg
June 19 - supplies were delivered today.   I see siding!
Is that enough wood to build a whole room ?
518.jpg

 519.jpg
June 25 - 29  -  edging trim was installed along the roof line,
corner edges, and framing around a few windows.
 
0556.jpg
 
0557.jpg  0558.jpg
July 2  -  starting to dig trench for sewer lines.

0560.jpg
July 3  -  finished trimming out the small windows of the house.
Installed trim around front door (sure miss my screen doors) 
0563.jpg
July 5  -  Dug trench for footings on the new addition. 
(I'm already thinking we should have made it bigger)
 
0562.jpg
 
0561.jpg
 
July 6  -  Trim installed around front window 
0566.jpg
 
July 9-10  -  Removed and replaced rotted boards around
base of house under utility room and tonka room. 
0576.jpg
Unfortunately they found termites again under the sliding door.
Going to have to have the ground and house treated again.
 
July 12-13  -  Finally started putting siding on! 
 
0564.jpg   0567.jpg 
 
July 16-17  -  Installed siding across front of house!
Can’t hardly believe it! 
0572.jpg
 
0574.jpg
July 18  -  Placed footing in trench       
       does that mean cement soon???
18_0577.JPG  19_0578.JPG
18_0579.JPG
July 19  -  Finished installing siding on front of house.
19_0582.JPG
 
19_0583.JPG
 
19_0581.JPG
 
July 20  -  Ray fired the crew!  
Starting Monday Ray will be here making
sure things get done.
 
July 23  -  Installed new vent on side of house.
Started siding along back of house.
27_0599.JPG   19_0580.JPG
 
July 24  -  What a difference it makes to have the boss on the job!
 
Took out the dryer, removed window in utility room,cut both door
openings and tore off outside wall to the studs.
0596.JPG 0595.JPG 0594.JPG
       0593.JPG 0592.JPG  
July 26 - Removed washer, cut out the drywall
(going to re-plumb pipes inside the wall),
tore up section of floor needing to be replaced.
27_0602.JPG 27_0600.JPG
July 27  -  Plumbing installed for new bathroom
27_0597.JPG 27_0598.JPG
and new wood put on outside wall
0590.JPG
July 28  -  Siding finished on side of house
03_0627.jpg 
 
July 28-29  decided to replace the entire floor in the utility room
so Rick & I spent the weekend tearing out the remaining
floor, treating the wood, and putting down insulation.
 
 28_0604.JPG 28_0605.JPG
28_0606.JPG 28_0609.JPG
28_0607.JPG 28_0608.JPG
July 30  -  Cement foundation poured!
 
30_0611.JPG
 
July 31  -  New flooring going down in utility room,
re-plumbing of the washer started
 
31_0615.JPG 31_0614.JPG
more siding installed along back of house
 
31_0618.JPG
  hot water heater moved to new location
(will be enclosed in it's own closet in new room)
insulation board going in around foundation
 
31_0617.JPG 
August 1  -  new outside entry door installed in utility room,
 
01_0619.JPG 01_0621.JPG
 
filled in trench along foundation
 
01_0620.JPG
 
August 2  -  siding completed as far as it can be along back
 
02_0623.JPG
 
August 2  -  Utility room outlets & switches installed
August 3  -  Utility room outlets wired, plumbing completed,
 
03_0629.jpg
 roof overhang removed
 
 03_0628.JPG
August 6  - Utility room electrical inspection passed!
Oh my gosh, they started framing the walls
this might actually get done  laugh3.gif
06_0630.jpg  06_0631.jpg
 and cut away more on the roof line
 
06_0631_2.jpg
 
August 7 - Framing of the walls installed
 
7_0632.jpg  7_0633.jpg  
7_0634.jpg 
 
August 8 - We got walls!
 
 8_0635.jpg 8_0636.jpg 
bathroom area laid out 
 
8_0637.jpg
 
August 9 - things are moving right along
 
9_0640.jpg  9_0641.jpg 
9_0642.jpg
 
9_0639.jpg  9_0638.jpg
August 10 - Trusses going up
 
10_0647.JPG  10_0648.JPG
10_0643.JPG 10_0644.JPG
10_0646.JPG 10_0645.JPG
August 13 - Decided to add a door, just looked like it should
have a door there. This will open onto the covered patio.
13_0649.JPG
 
August 14 - Roof starting to go on
 
14_0650.JPG 14_0652.JPG 
14_0651.JPG
August 16 - Starting false roof to connect the three
different levels of rooflines  
16_0654.JPG
August 17 - Heating ductwork laid out.
False roof basically finished, felt installed on roof.
Dug out ground for patio and sidewalk along addition.
 17_0659.JPG 17_0658.JPG 17_0660.JPG 
 17_0657.JPG 817_0656.JPG 17_0655.JPG 
August 18 thru 24 - got my washer and dryer back
 
824_0678.JPG  
insulation going in on the addition  
 824_0672.JPG 824_0673.JPG 824_0674.JPG
 824_0675.JPG  framing for hot water heater closet going up
  August 25 & 26 - roofing on the addition installed     
825_0682.JPG 
825_0681.JPG
August 27 - new bedroom door installed - has paper over it to
protect glass this door will open onto the new patio
 8027_0690.JPG
they got all the insulation in
  8027_0683.JPG 8027_0684.JPG 8027_0685.JPG 8027_0686.JPG 
August 28 - most of the sheet rock put up, framing in place for
bi-fold door to cover washer & dryer
8028_0692.JPG 8028_0693.JPG 8028_0694.JPG 
August 29 - sheet rock on the bathroom wall   
 829_0700.JPG 829_0699.JPG 
pocket door installed - this is the door into the "new"
utility room (sheet rock yet to come)  second picture is standing in
the utility room looking to new laundry area 
 829_0696.JPG 829_0697.JPG
   below 1st picture is standing in original part of house looking
down "new" hallway (once it's sheet rocked) into new addition. 
Second picture is standing in the new addition looking down
new hallway to the 'tonka' room.
829_0698.JPG    829_0701.JPG
dug out lawn for the sidewalk leading to the garage
(Rick has been wanting this for 20 years)
829_0695.JPG
 August 30 -  Drywall up, taped and mudded on the
inside of the hot water heater closet
 
   830_0704.JPG  830_0702.JPG
Installed bathroom floor (covered with cardboard for protection)
installed shower walls. 
 
830_0705.JPG    830_0706.JPG
August 31 -  finished installing drywall, passed inspection!
 
831_0707.JPG  831_0710.JPG 
831_0708.JPG  831_0709.JPG
September 1 - 5    taping, mudding, & sanding drywall
 
905_711.JPG 905_712.JPG 905_714.JPG
905_715.JPG 905_716.JPG
September 6-13   finished installing all the siding!
 
906_717.JPG 909_722.JPG 909_721.JPG
910_724.JPG 913_726.JPG 913_0727.JPG
must be all most done - all the piles of wood are gone from
the driveway.   Going to re-locate our gate here.
 
909_723.JPG
 
 Sept. 14  preparing for texturing
 
 914_726.jpg  914_730.JPG
 
Sept. 15-17   Textured, primed and painted inside walls.
Installed shower walls.
 
917_731.JPG 917_732.JPG 917_733.JPG
 Sept.18-19   Taped off outside windows and doors
preparing to paint.  Set up the bathroom pieces
918_736.JPG
 
Sept. 20-21   The house is painted!  Light green with bit darker trim
 
 920_741.JPG
   920_739.JPG 920_740.JPG
920_7392.JPG
 
 
 


 